SwePol
Template:Short description Template:Use British English Template:Use dmy dates Template:Infobox power transmission line SwePol is a Template:Convert-long monopolar high-voltage direct current (HVDC) submarine cable between the Stärnö peninsula near Karlshamn, Sweden, and Bruskowo Wielkie, near Słupsk, Poland.[1] The link was inaugurated in 2000 and can transmit up to 600 MW power at a voltage of 450 kV.
The cable has a cross section of Template:Convert. It runs for Template:Convert as an underground cable from the Stärno HVDC Station to the shore of the Baltic Sea. The Template:Convert long submarine cable comes ashore in Poland near Ustka at Template:Coord and runs underground for the remaining Template:Convert to Bruskowo Wielkie HVDC Static Inverter Plant.
Unlike other monopolar HVDC schemes, Swepol uses a metallic return consisting of 2 cables with Template:Convert sections for the submarine portion of the line, and a single cable with Template:Convert sections for the land portions.
Both stations use air-core inductance smoothing rectifiers of 225 mH and a weight of Template:Convert, with filters for the 11th, 13th, 24th, and 36th harmonics. Each filter consists of a coil and a capacitor switched in row. The filters for the 11th and 13th harmonics are adjustable. The filters deliver a reactive power of 95 Mvar. Additional 95 Mvar reactive power is delivered by a capacitor bank. Each station's static inverter, which is switched as a 12-pulse thyristor bridge, consists of 792 thyristors arranged in three Template:Convert high towers installed in a valve hall.
It was initially owned and maintained by SwePol Link AB, a company jointly owned by the state-owned Swedish power company Svenska Kraftnät (51%), Vattenfall (16%), and Polish transmission system operator PSE-Operator (33%), but the company was liquidated and the cable was acquired by Svenska Kraftnät for the Swedish and PSE-Operator for the Polish part of the cable.
Since coming online, 11 instances of cable damage have occurred: one on the high voltage line and 10 on the return cable. Causes have included ship anchors, fishing nets, fire, and grid power disturbances. On 14 February 2005, the smoothing reactor at the HVDC station at Bruskowo Wielkie was destroyed by fire. Repairs took 20 hours.
Initially SwePol was used to export electricity to Poland only.
From January to October 2020 Poland exported 1,225.9 GWh of electricity and imported 12,573.1 GWh compared to 872.8 GWh and 9,326.7 GWh in the same period 2019. The largest import was from Germany 3,222.2 GWh, Sweden 3,195.9 GWh and the Czech Republic 2,561.5 GW.[2] Poland's power market will face a supply squeeze from 2025, when a tightening of EU rules on plants’ Template:CO2 emissions will force nearly 5 GW of thermal capacity out of the system, the nation's TSO has warned.[3]
When the Nord Stream gas pipeline, also in the Baltic Sea, began to leak in September 2022 and sabotage was suspected, many people feared that the SwePol link had also been damaged. Tests by Svenska Kraftnät, published on 4 October the same year, indicated that was not the case.[4]
Annual reports
In 2016, SwePol had an available technical capacity of 87%. The technical capacity not used was 25%. Totally, 2.8 TWh (52.4% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (3.3% of the technical capacity) was imported to Sweden.[5]
In 2017, SwePol had an available technical capacity of 94.2%. The technical capacity not used was 31.9%. Totally, 3.1 TWh (59.4% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (2.9% of the technical capacity) was imported to Sweden.[6]
In 2018, SwePol had an available technical capacity of 96%. The technical capacity not used was 30%. Totally, 3.1 TWh (59% of the technical capacity) was exported from Sweden to Poland and 0.4 TWh (7% of the technical capacity) was imported to Sweden.[7]
In 2019, SwePol had an available technical capacity of 86%. The technical capacity not used was 24%. Totally, 3.1 TWh (59% of the technical capacity) was exported from Sweden to Poland and 0.2 TWh (4% of the technical capacity) was imported to Sweden. SwePol transmitted 62% of its technical capacity, which is slightly less than in 2018 but still higher than the average utilisation since 2012. The available capacity was lower than normally due to an unplanned maintenance outage and a disturbance outage. The unplanned maintenance outage was caused by an oil leakage and the disturbance outage was caused by a valve cooling system failure lasting 29 days.[8]
In 2020, SwePol had an available technical capacity of 87%. The technical capacity not used was 13%. Totally, 3.8 TWh (72% of the technical capacity) was transmitted south from Sweden to Poland and >0.1 TWh (0.2% of the technical capacity) was transmitted north to Sweden. The annual maintenance of SwePol lasted 6 days in September. Additionally, SwePol had 3 other planned maintenance outages and 1 other outage during 2020. SwePol had 3 minor disturbance outages and 1 more severe disturbance outage in 2020. The severe disturbance outage was caused by a fire in the AC filter on the Polish side in January, and it took 19 days to bring the HVDC link back online after it.[9]
In 2021, SwePol had an available technical capacity of 91%. The technical capacity not used was 22%. Totally, 3.4 TWh (65% of the technical capacity) was transmitted south (SE4→PL) and 0.2 TWh (4% of the technical capacity) was transmitted north (PL→SE4). The annual maintenance of SwePol lasted 6 days in September. Additionally, SwePol had 10 other planned maintenance outages during 2021. There were 5 minor disturbance outages, of which one lasted more than 8 hours. SwePol was offline due to disturbance outages for 49 hours in total in 2021. [10]
In 2022, SwePol had an available technical capacity of 87%. The technical capacity not used was 11%. Totally, 3.9 TWh (74% of the technical capacity) was transmitted south (SE4→PL) and 0.1 TWh (2% of the technical capacity) was transmitted north (PL→SE4). Swepol experienced a total of 23 outages, comprising 17 maintenance outages and 6 disturbances. Among the maintenance outages, a majority of them were brief and conducted for corrective maintenance purposes, even though the specific reasons behind these mainte nance requirements remained unclear. The annual maintenance period for SwePol occurred over a duration of 29 days, spanning September and October. This extended maintenance period led to a decrease in the available technical capacity, which dropped to 87,3%. [11]
In 2023, SwePol had an available technical capacity of 90%. The technical capacity not used was 13%. Totally, 4.0 TWh (77% of the technical capacity) was transmitted south (SE4→PL) and 0.3 TWh (5% of the technical capacity) was transmitted north (PL→SE4). Swepol experienced a total of 20 outages, comprising 17 planned maintenance outages and 3 disturbances outages. Among the maintenance outages, a majority of them were brief and conducted for corrective maintenance. The specific reasons for these maintenances have in many cases not been reported. Reported reasons are for instance AC busbar maintenance and control center maintenance. The annual maintenance for SwePol took place during 13 days in October and the available technical capacity during the year was approximately 90%. [12]
Sites
| Site | Coordinates |
|---|---|
| Bruskowo Wielkie Static Inverter Plant | Template:Coord |
| Stärnö Static Inverter Plant | Template:Coord |
Cultural meaning
Swepol Link is also the name of a local soccer team in the town of Bruskowo Wielkie.[13]
See also
Script error: No such module "Portal".
- Energy in Poland
- Electricity sector in Sweden
- List of high-voltage transmission links in Sweden
- Estlink, cable between Estonia and Finland
- LitPol Link, cable between Lithuania and Poland
- Harmony Link, subsea cable between Lithuania and Poland
References
External links
Template:More footnotes needed Template:GeoGroup
- SwePol Link AB
- PSE-SwePol Link
- The ABB Group: SwePol
- Site on GeoPortal
- A cable marker on Google Street View
- Skyscraperpage.com
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- ↑ Script error: No such module "citation/CS1".
- Pages with script errors
- Electrical interconnectors to and from the Nordic grid
- Electrical interconnectors to and from the Synchronous Grid of Continental Europe
- Energy infrastructure completed in 2000
- Submarine power cables
- Electric power infrastructure in Poland
- Electric power infrastructure in Sweden
- Connections across the Baltic Sea
- HVDC transmission lines
- Poland–Sweden relations
- 2000 establishments in Poland
- 2000 establishments in Sweden